JavaScript must be enabled in order for you to use the Site in standard view. However, it seems JavaScript is either disabled or not supported by your browser. To use standard view, enable JavaScript by changing your browser options.

| Last Updated:: 01/02/2016

Coal & Lignite 2014-15

 

Company-wise details of coal production are provided in the table below:

 

Company 2013-14
Actual
2014-15
Target
2014-15 (Actual)
(Apr-Dec.14)
Achievement
(%)
Growth (%)
(Apr-Dec.14)
CIL 462.41 507.00 342.4 67.5 7.3
SCCL 50.47 55.00 35.2 64.0 3.2
Captive 39.91 50.00 40.1 80.2 42.7
Others 12.98 18.00 9.1 50.5 -7.2
Total 565.77 630.25 426.7 67.7 9.1

Note: Figures for 2014-15 are provisional

 

 

Company wise Raw Coal Dispatch is given below:

 

Company April-December, 2013
Actual
April - December, 2014 % growth
Target Actual
CIL 341.25 376.34 354.33 3.8
SCCL 34.26 40.20 38.24 11.62

 

 

Sector wise Raw Coal Dispatch (provisional) - CIL:

(In Million Tonne)

Sector April- December,
2013
April- December,
2014
Growth % January –March,
2014
January –March,
2015 (Esmtd.)
%Growth
Steel * 5.81 4.92 -15.3% 2.05 1.75 -14.6%
Power
(Utility )**
256.10 280.38 9.5% 98.52 107.48 9.1%
Power
(Captive) $
22.62 20.83 -7.9% 7.16 6.80 -4.9%
Cement 3.93 4.04 2.8% 1.52 1.54 1.3%
Fertilizer $ 1.70 1.62 -4.9% 0.58 0.56 -3.7%
Others $ 51.08 42.54 -16.7% 20.02 16.25 -18.8%
CIL 341.25 354.33 3.8% 129.85 134.39 3.5%

*includes coking coal feed to washeries, direct feed, blendable to steel plants, coke ovens, private cokeries and NLW coal to cokeries. Negative growth in dispatch arising out of dwindling availability of requisite quality and quantity of raw coal and due to reduced capacity of the old washeries.

 

**includes non-coking coal feed to washery and Bina Descaling Plant for beneficiation

 

$ Negative growth in dispatch to various sectors arising out of increased number of commissioned power stations leading to higher demand and priority dispatch of coal to power utilities

 

# excludes colliery consumption

 

 

Sector wise Dispatch - SCCL:

(In Million Tonne)

Sector April- December,
2013
April- December,
2014
Growth %
Power (utility & CPP) 25.98 30.00 15.47
Steel (Sponge Iron) 0.26 0.27 3.85
Cement 3.70 3.46 (-) 6.73
Fertilizer - - -
Others 4.32 4.51 4.64
Total : SCCL 34.26 38.24 11.62

 

 

Lignite Production:

 

Production of Lignite and Power by NLC
Item 2013-14
Actual
2014-15
Target
2014-15 (Actual)
(upto 31/12/2014)
Achievement (%) Growth (%)
Lignite MT 26.61 25.60 17.15 66.99 -6.9
Power Generation (MU) 19967.72 20285.00 14201.93 70.01 -1.3

 

 

Sector wise breakup of actual supply of coal vis-à-vis the demand as estimated at the beginning of 2014-15:

(In million tonnes)

  Sector 2011-12
Actual
2012-13
Actual
2013-14
Actual #
2014-15
Est Demand
2014-15
Actual (Apr-Nov)
I. Coking Coal  
1 Steel / Coke Oven & Cokeries (Indigenous) 15.53 16.90 23.13 17.02 11.34
2 Steel (Import) 31.80 35.56 37.19 38.44 27.62
  Sub Total 47.33 52.46 60.32 55.46 38.96
II. Non Coking Coal  
3 Power (Utilities) 412.44 457.43 482.33 551.60 365.89
4 Power (Captive) 46.51 55.05 42.41 50.00 33.17
5 Cement 22.57 22.39 23.85 26.12 17.33
6 Sponge Iron/ CDI 21.69 20.90 15.12 23.85 15.82
7 BRK & Others .including Fertilizer 88.19 107.95 115.66 80.00 53.06
  Sub Total 591.40 662.94 679.37 731.57 485.27
  Total Raw Coal 638.73 713.39 739.69 787.03 524.23
Source: Annual Plan, Ministry of Coal 2014-154, Coal Controller Organisation

 

 

Coal Supply and Demand :

(In Million Tonne)

Source 2013-14
Target/Estimate
2013-14
Actual
2014-15
Target/Estimate
2014-15 Actual
(upto Nov, 2014)
CIL 492.00 471.50 520.00 310.70
SCCL 56.00 47.94 55.50 33.50
Others 66.55 51.56 68.25 42.40
Total indigenous supply 614.55 571.00 643.75 386.60
Demand projected/ Actual supply
(Domestic + Import)
769.69 739.50 787.03 524.20
Import–
Estimated / Actual
155.14 168.50 143.28 137.60
Note: Demand is assessed by the Planning Commission at the beginning of each Annual Plan where as the supply figures are based on actual as realized by the end of the reporting period

 

 

Company wise production of Coal :

(In Million Tonne)

Company 2011-12
(Actual)
2012-13
(Actual)
2013-14
(Actual)
2014-15
Target
2014-15 (Actual)
(upto Dec.2014)
ECL 30.56 33.91 36.05 38.00 26.73
BCCL 30.21 31.21 32.61 34.00 24.57
CCL 48.00 48.06 50.02 55.00 36.49
NCL 66.40 70.02 68.64 77.00 48.38
WCL 43.11 42.29 39.73 44.00 28.62
SECL 113.84 118.22 124.26 131.00 90.18
MCL 103.12 107.89 110.44 127.00 87.11
NEC 0.60 0.61 0.66 1.00 0.30
CIL 435.84 452.21 462.41 507.00 342.37
SCCL 52.21 53.19 50.47 55.00 35.24
Others 51.90 51.00 52.89 68.25 49.10
Total 539.95 556.40 565.77 630.25 426.71
*Provisional

 

 

Lignite Production and Power Generation:

 

Year Lignite (in MT) Power Generation (in MU)
2011-12 (Actual) 24.59 18789.44
2012-13 (Actual) 26.22 19902.34
2013-14 (Actual) 26.61 19988.65
2014-15 (BE) 25.60 20285.00
2014-15 (Actual)* (Apr- Dec.2014) 17.15 14201.93
2015-16 (BE) 25.67 20944.52
*Provisional

 

 

(Source: Annual Report 2014-15: Ministry of Coal)