Envis Centre, Ministry of Environment & Forest, Govt. of India
Printed Date: Friday, December 27, 2024
Coal & Lignite 2014-15
Company-wise details of coal production are provided in the table below:
Company |
2013-14
Actual |
2014-15
Target |
2014-15 (Actual)
(Apr-Dec.14) |
Achievement
(%) |
Growth (%)
(Apr-Dec.14) |
CIL |
462.41 |
507.00 |
342.4 |
67.5 |
7.3 |
SCCL |
50.47 |
55.00 |
35.2 |
64.0 |
3.2 |
Captive |
39.91 |
50.00 |
40.1 |
80.2 |
42.7 |
Others |
12.98 |
18.00 |
9.1 |
50.5 |
-7.2 |
Total |
565.77 |
630.25 |
426.7 |
67.7 |
9.1 |
Note: Figures for 2014-15 are provisional
Company wise Raw Coal Dispatch is given below:
Company |
April-December, 2013
Actual |
April - December, 2014 |
% growth |
Target |
Actual |
CIL |
341.25 |
376.34 |
354.33 |
3.8 |
SCCL |
34.26 |
40.20 |
38.24 |
11.62 |
Sector wise Raw Coal Dispatch (provisional) - CIL:
(In Million Tonne)
Sector |
April- December,
2013 |
April- December,
2014 |
Growth % |
January –March,
2014 |
January –March,
2015 (Esmtd.) |
%Growth |
Steel * |
5.81 |
4.92 |
-15.3% |
2.05 |
1.75 |
-14.6% |
Power
(Utility )** |
256.10 |
280.38 |
9.5% |
98.52 |
107.48 |
9.1% |
Power
(Captive) $ |
22.62 |
20.83 |
-7.9% |
7.16 |
6.80 |
-4.9% |
Cement |
3.93 |
4.04 |
2.8% |
1.52 |
1.54 |
1.3% |
Fertilizer $ |
1.70 |
1.62 |
-4.9% |
0.58 |
0.56 |
-3.7% |
Others $ |
51.08 |
42.54 |
-16.7% |
20.02 |
16.25 |
-18.8% |
CIL |
341.25 |
354.33 |
3.8% |
129.85 |
134.39 |
3.5% |
*includes coking coal feed to washeries, direct feed, blendable to steel plants, coke ovens, private cokeries and NLW coal to cokeries. Negative growth in dispatch arising out of dwindling availability of requisite quality and quantity of raw coal and due to reduced capacity of the old washeries.
**includes non-coking coal feed to washery and Bina Descaling Plant for beneficiation
$ Negative growth in dispatch to various sectors arising out of increased number of commissioned power stations leading to higher demand and priority dispatch of coal to power utilities
# excludes colliery consumption
Sector wise Dispatch - SCCL:
(In Million Tonne)
Sector |
April- December,
2013 |
April- December,
2014 |
Growth % |
Power (utility & CPP) |
25.98 |
30.00 |
15.47 |
Steel (Sponge Iron) |
0.26 |
0.27 |
3.85 |
Cement |
3.70 |
3.46 |
(-) 6.73 |
Fertilizer |
- |
- |
- |
Others |
4.32 |
4.51 |
4.64 |
Total : SCCL |
34.26 |
38.24 |
11.62 |
Lignite Production:
Production of Lignite and Power by NLC |
Item |
2013-14
Actual |
2014-15
Target |
2014-15 (Actual)
(upto 31/12/2014) |
Achievement (%) |
Growth (%) |
Lignite MT |
26.61 |
25.60 |
17.15 |
66.99 |
-6.9 |
Power Generation (MU) |
19967.72 |
20285.00 |
14201.93 |
70.01 |
-1.3 |
Sector wise breakup of actual supply of coal vis-à-vis the demand as estimated at the beginning of 2014-15:
(In million tonnes)
|
Sector |
2011-12
Actual |
2012-13
Actual |
2013-14
Actual # |
2014-15
Est Demand |
2014-15
Actual (Apr-Nov) |
I. |
Coking Coal |
|
1 |
Steel / Coke Oven & Cokeries (Indigenous) |
15.53 |
16.90 |
23.13 |
17.02 |
11.34 |
2 |
Steel (Import) |
31.80 |
35.56 |
37.19 |
38.44 |
27.62 |
|
Sub Total |
47.33 |
52.46 |
60.32 |
55.46 |
38.96 |
II. |
Non Coking Coal |
|
3 |
Power (Utilities) |
412.44 |
457.43 |
482.33 |
551.60 |
365.89 |
4 |
Power (Captive) |
46.51 |
55.05 |
42.41 |
50.00 |
33.17 |
5 |
Cement |
22.57 |
22.39 |
23.85 |
26.12 |
17.33 |
6 |
Sponge Iron/ CDI |
21.69 |
20.90 |
15.12 |
23.85 |
15.82 |
7 |
BRK & Others .including Fertilizer |
88.19 |
107.95 |
115.66 |
80.00 |
53.06 |
|
Sub Total |
591.40 |
662.94 |
679.37 |
731.57 |
485.27 |
|
Total Raw Coal |
638.73 |
713.39 |
739.69 |
787.03 |
524.23 |
Source: Annual Plan, Ministry of Coal 2014-154, Coal Controller Organisation |
Coal Supply and Demand :
(In Million Tonne)
Source |
2013-14
Target/Estimate |
2013-14
Actual |
2014-15
Target/Estimate |
2014-15 Actual
(upto Nov, 2014) |
CIL |
492.00 |
471.50 |
520.00 |
310.70 |
SCCL |
56.00 |
47.94 |
55.50 |
33.50 |
Others |
66.55 |
51.56 |
68.25 |
42.40 |
Total indigenous supply |
614.55 |
571.00 |
643.75 |
386.60 |
Demand projected/ Actual supply
(Domestic + Import) |
769.69 |
739.50 |
787.03 |
524.20 |
Import–
Estimated / Actual |
155.14 |
168.50 |
143.28 |
137.60 |
Note: Demand is assessed by the Planning Commission at the beginning of each Annual Plan where as the supply figures are based on actual as realized by the end of the reporting period |
Company wise production of Coal :
(In Million Tonne)
Company |
2011-12
(Actual) |
2012-13
(Actual) |
2013-14
(Actual) |
2014-15
Target |
2014-15 (Actual)
(upto Dec.2014) |
ECL |
30.56 |
33.91 |
36.05 |
38.00 |
26.73 |
BCCL |
30.21 |
31.21 |
32.61 |
34.00 |
24.57 |
CCL |
48.00 |
48.06 |
50.02 |
55.00 |
36.49 |
NCL |
66.40 |
70.02 |
68.64 |
77.00 |
48.38 |
WCL |
43.11 |
42.29 |
39.73 |
44.00 |
28.62 |
SECL |
113.84 |
118.22 |
124.26 |
131.00 |
90.18 |
MCL |
103.12 |
107.89 |
110.44 |
127.00 |
87.11 |
NEC |
0.60 |
0.61 |
0.66 |
1.00 |
0.30 |
CIL |
435.84 |
452.21 |
462.41 |
507.00 |
342.37 |
SCCL |
52.21 |
53.19 |
50.47 |
55.00 |
35.24 |
Others |
51.90 |
51.00 |
52.89 |
68.25 |
49.10 |
Total |
539.95 |
556.40 |
565.77 |
630.25 |
426.71 |
*Provisional |
Lignite Production and Power Generation:
Year |
Lignite (in MT) |
Power Generation (in MU) |
2011-12 (Actual) |
24.59 |
18789.44 |
2012-13 (Actual) |
26.22 |
19902.34 |
2013-14 (Actual) |
26.61 |
19988.65 |
2014-15 (BE) |
25.60 |
20285.00 |
2014-15 (Actual)* (Apr- Dec.2014) |
17.15 |
14201.93 |
2015-16 (BE) |
25.67 |
20944.52 |
*Provisional |
(Source: Annual Report 2014-15: Ministry of Coal)