JavaScript must be enabled in order for you to use the Site in standard view. However, it seems JavaScript is either disabled or not supported by your browser. To use standard view, enable JavaScript by changing your browser options.

| Last Updated:: 20/04/2018

Coal & Lignite 2016-17

 

 

Graphical Representation

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Tabular Values

 

 Company wise Raw Coal Dispatch:

 

Company
Apr’17- Dec’17
Apr’16-Dec’16
%
growth
Target
Actual
% achievement
Actual
CIL              
431.93
421.22
98
391.58
7.6
SCCL
62.00
41.99
67.72
61.34
-1.01

 

 

 Sector wise Raw Coal Dispatch (Provisional):

 

(In Million tonnes)
Sector
Apr’17-Dec’17
Apr’16-Dec’16
% growth in Apr’17-Dec’17 over Apr’16-Dec’16
Steel *
4.11
4.84
-15.0%
Power ( Utility )**
331.44
308.24
7.5%
Power( Captive) ***
29.02
22.47
29.2%
Cement
2.95
2.64
11.9%
Others
53.69
53.39
0.6%
CIL #
421.22
391.58
7.6%

* includes coking coal feed to washeries, direct feed and blendable to steel plants
** includes non-coking coal feed to washery and Bina Deshaling Plant for beneficiation and special forward e-auction to power
*** Captive Power includes despatches to fertilizer sector
# excludes colliery consumption

 

 

 Sector wise Raw coal Dispatch (Jan-Mar’18 projection on BE basis):

 

(In Million tonnes)
Sector
Jan’18-Mar’18
Jan’17-Mar’17
% growth in Jan’18-Mar’18 over Jan’17-Mar’17
Steel *
2.00
1.92
4.2
Power ( Utility )**
128.95
118.05
9.2
Power( Captive)#
14.09
8.38
68.1
Cement
1.98
1.04
90.7
Others
31.52
22.09
42.7
CIL
178.54
151.47
17.9

* includes coking coal feed to washeries, direct feed and blendable to steel plants,
** includes non-coking coal feed to washery and Bina Deshaling Plant for beneficiation and special forward e-auction to power
# Captive Power includes dispatches to fertilizer sector

 

 

 Sector wise Dispatch- SCCL:

 

(In Million tonnes)
Sector
April – December 2017
April – December 2016
Growth (%)
January –March 17 (Anticipated)
2017-18
(Anticipated)
Power (utility)
38.89
36.46
6.68
14.99
53.88
Power (CPP)
2.03
1.25
61.95
0.75
2.78
Steel (SI)
0.160
0.06
183.93
0.15
0.31
Cement
1.87
1.48
26.15
0.70
2.57
Others
3.91
3.45
13.44
1.54
5.46
Total : SCCL
46.86
42.70
9.75
18.14
65.00

 

 

 Supply of Coal in 2017-18 :

 

(Fig. in Million Tonne)
Sl. No.
Sector
2012-13
Actual
2013-14
Actual
2014-15
Actual
2015-16
Actual
2016-17
Actual (Prov.)
2017-18
Estimated Demand
2017-18
Actual
April-Dec. (P)
I.
Coking Coal
 
 
 
 
1
Steel / Coke Oven Cokeries (Indigenous)
&
15.50
15.49
12.02
12.27
12.50
-
10.66
2
Steel (Import)
35.56
36.87
43.72
44.56
41.64
-
26.95
 
Sub Total
51.06
52.36
55.74
56.83
54.14
63.17
37.61
II.
Non Coking Coal
 
 
 
 
3
Power (Utilities)
387.77
394.53
435.44
483.12
496.57
622.96
384.88
4
Power (Captive)
59.00
54.42
62.26
34.65
30.68
90.34
23.865
5
Cement
22.38
21.02
11.36
8.99
6.43
22.32
5.017
6
Sponge Iron/ CDI
20.90
18.49
17.77
7.76
5.68
24.61
4.27
7
BRK & Others .including Fertilizer
172.27
198.52
239.57
245.37
248.05
85.00
165.62
 
Sub Total
662.33
686.98
766.39
779.89
787.41
845.23
583.65
 
Total Raw Coal
713.39
739.34
822.13
836.73
841.56
908.40
621.26
 
P=Provisional,
 
 
Source :Coal Controller Organisation