C o n t e n t s
- Constitution of Inspection Committee and ToR
- Background of Clearances Granted
- 2.1 Mundra Port Area (Mundra Port and SEZ Limited)
- 2.2 Power Project (Adani Power Limited)
- 2.3 Mundra SEZ, Forest and Airport Clearances
- Examination of Issues: Specific Environmental Impacts
- 3.1 Diversion, Blocking of Creeks and Reclamation to Distort HTL
- 3.2 Destruction of Mangroves and Leveling of Sand Dunes
- 3.3 Handling of Fly Ash
- 3.4 Earthquake/Tsunami and Project Clearance
- 3.5 Salinity Ingress and impact on agriculture
- Compliance with Environment and Forest Conditions
- 4.1 Development and Compliance for Port, Roads (Waterfront Development)
- 4.2 Development and Compliance for Thermal Power Plant
- HTL Line Demarcation
- 5.1 Possible HTL Violations in Construction of Samundra Township and Sterling Hospital
- 5.2 Possible HTL/LTL Violation in Project Area
- Critical Issues not in ToR
- 6.1 Fishermen Livelihood and Access to Fishing Grounds
- 6.2 Village Common Land (Gauchar)
- 6.3 Cumulative Impacts of Power Plants and Port Projects
- Summary of Observations and Recommendations
- 7.1 Overall Observations and Assessment
- 7.2 Recommendations for effective deterrence for non-compliance and remedial measures
- 7.3 Specific recommendations on reform of CRZ regulations/li>
- 7.4 Specific recommendations on project clearance conditions and post clearance monitoring
For The Complete Report: CLICK HERE