JavaScript must be enabled in order for you to use the Site in standard view. However, it seems JavaScript is either disabled or not supported by your browser. To use standard view, enable JavaScript by changing your browser options.

  • Bibliography
| Last Updated: :25/04/2024

BIBLIOGRAPHY

Title : INFRASTRUCTURE DEVELOPMENT IN HIGHLY JOINTED GROUND AT THE NEW AFTON BLOCK CAVE MINE
Subject : Mining Infrastructure
Volume No. : xxx
Issue No. : 
Author : Ferrin Prince, Tyler Roberts, and Kurt Keskimaki
Printed Year : 2013
No of Pages  : 11
Description : 

New Gold’s New Afton mine is an 11,000 tonne per day block caving mine, located 8 km west of the city of Kamloops, British Columbia. The reserve is estimated at 52.5Mt with grades of 0.65 g/t Au and 0.93% Cu. Block caving requires a considerable amount of infrastructure development before production can begin. Each excavation had its own challenges, often further complicated by interactions with the caving stresses and fault structures. The main areas of interest were: the production crusher complex, the surface to underground infrastructure, and the footprint interaction with the faults. The ore zone at New Afton is bounded by two very weak fault zones, with large fault affected areas and associated splays. The resulting rock mass rating (RMR) is 35-50, with some areas significantly weaker due to clay infill. These conditions created a unique and decidedly difficult environment in which to develop New Afton’s infrastructure. Despite these difficulties, the mine began production on schedule in July 2012. The main production crusher for the mine is a gyratory crusher that allows for direct truck dumping, with a smaller jaw crusher in series to facilitate the initial development and production. The crusher chamber was redesigned several times to minimize the chamber volume, resulting in a 40% decrease in volume without losing functionality. After drilling and geotechnical testing, the location of the crusher was changed to eliminate the threat of fault affected ground in the area; the entire complex moved a short time before mining began on the chamber. The mining techniques used enabled tight control of the crusher pocket excavation, while also allowing for the timely completion of the chamber. The locations of the surface to underground infrastructure were tightly constrained by geology, surface infrastructure, and an existing open pit. The VR5 raise was drilled and abandoned part way through the reaming process when the drill string became stuck in fault gouge material. It was relocated and successfully completed. The VR7 raise hit a region of poor rock strength and deviated more than 11 m. Poor ground conditions caused a 130m section of the raise walls to fail. An innovative rehabilitation program was undertaken to re-establish the raise for ventilation. A surface to underground slick line was also installed to ease the material movement underground. A layout of the Extraction level was changed from herring bone to straight through drawpoints that resulted in a net reduction of 1.3 km of development. The Apex level was added to aid in the breakage over the major apex pillar and allow for geological mapping. A portion of the caving footprint is located within the footwall fault. The low strength, high clay content, and small joint spacing of the material resulted in blast-hole cut-off and drift deformation. Drift rehabilitation was a key factor in the successful development of the cave footprint. Innovative drilling and loading techniques were used to keep the holes open and to impede movement along the joint structures.

 

Read The Complete Paper: CLICK HERE